When is a change out of the scope of the contract? Judge Marian Horn of the Court of Federal Claims (COFC) has written the definitive treatise on the rules used to decide when a change exceeds the scope of the original contract. Two types of facts are implicated. The first is when a contractor on an awarded contract complains the change is beyond the scope of the contract. The other is when a competitor complains that the change is beyond the scope of the original contract and, therefore, should, under the Competition in Contracting Act (CICA), be open for competition. Judge Horn had the latter complaint before her. In either case, however, the central question is whether the modified contract calls for essentially the same performance.
What is a cardinal change? A cardinal change occurs when the government alters the work so drastically that it requires the contractor to perform duties materially different from those initially needed. Just as the cardinal change doctrine prohibits an agency from compelling a contractor to perform beyond the scope of the original bargain, the CICA prevents an agency from ordering work materially different from the contract for which the competition was held.
What is "materially different"? Lack of resemblance to the original work. Substantial changes in the type of work, performance period, and cost. It's a question of fact for which there is no mechanical or arithmetical answer. The courts and boards look to changes to the quantity of work, an increase in the cost of the work, the sheer number of changes, the cumulative effect of the changes to the work, and changes to the time and place of the work.
But in the bid protest arena, there is another factor to consider. Did the solicitation for the original contract adequately advise the bidders of the potential for the type of changes that occurred? Is the modification of a nature that potential bidders would reasonably have anticipated? Is it something potential bidders would have expected to fall within the contract changes clause?
Suppose the court concludes as a matter of law that the modification was contemplated in the original procurement and the type of work, quantity, performance period, and costs have not substantially changed. CICA is not implicated in that case, and the protest will be dismissed. Which is precisely what Judge Horn did. Case dismissed.
The cardinal change doctrine articulates a firm set of rules. Whether you are a disgruntled bidder or a contractor tearing out your hair over the nature or size of a modification, you can avail yourself of the argument that you have encountered a cardinal change.
bill@spriggslawgroup.com
No comments:
Post a Comment