Friday, August 16, 2019

HELP WITH REA AND TERMINATION

We wish to remind the contractor community that we remain available to handle advice on REA's and claims, writing and review of REA's and claims, defending terminations for default and appeal of claims and terminations to the Boards of Contract Appeals.  We have an excellent track record for responsiveness, thoroughness and good results.  We charge at a modest hourly rate although we are now in a position to consider contingency fee arrangements.  Our standard hourly fee is $250.00 per hour.  We always provide estimates to complete which are then converted to not to exceed prices.  Evaluation and estimates are free.

We also handle protests at the agency level only.

bill@spriggsconsultingservices.com                    bill@spriggslawgroup.com

Monday, June 10, 2019

THE JUDICIAL ROLE OF THE CONTRACTING OFFICER REVISITED

We've written often about the role of the contracting officer.  We also have emphasized the judicial role they must play.  And yet, we continue to hear complaints that contracting officers are not even handed.  They are partisan advocates for the government and grand guardians of the public purse.  So.....

It's time we reminded ourselves of the judicial role of the contracting officer in government contracts.  Contracting officers are required by law to act impartially and function in a judicial role when resolving disputes.  The history is clear but very often overlooked.

Abraham Lincoln once said:  "It is as much the duty of the government to render prompt justice against itself, in favor of citizens, as it is to administer the same between private individuals."  In 1912, the United States Supreme Court, in addressing the duties of the contracting officer, said:  "But the very extent of the power and the conclusive character of his decision raised a corresponding duty that the agent's judgment should be exercised not capriciously or fraudulently, but reasonably, and with due regard to the rights of both contracting parties."

The most resounding pronouncement, however, was made by the Court of Claims in a 1950 opinion when, after referring to the 1912 Supreme Court opinion, the Court of Claims said the contracting officer must not represent either side but must "act as an impartial, unbiased judge."  The Court of Claims went on to say the contracting officer's function was "to act impartially, weighing with an even hand the rights of the parties on the one hand and on the other."  The court recognized the obligation of the contracting officer to represent the government's interests in procurement matters, but it went on to state clearly that "in settling disputes this is not his function." 

This is pretty clear.  So why are there so many complaints about contracting officers failing to act judicially when disputes arise?

It's time to get back to basics and take heed of judicial precedent.  And just to bring all this up to date, read FAR 1.602-2(b) again.  "Contracting officers shall ensure that contractors receive impartial, fair and equitable treatment."  It's mandatory.  Impartial, fair and equitable treatment.  Sounds like something Abraham Lincoln might have said.

If you want to read more on this subject and see all the citations to case law, send us an email and we will send you a law journal article which covers the details.

bill@spriggsconsultingservices.com                  bill@spriggslawgroup.com     

Sunday, June 9, 2019

WHEN TO APPEAL A DEFAULT TERMINATION

The Armed Services Board of Contract Appeals (ASBCA) enforces the 90 day statutory appeal requirement of terminations for default (or cancellation).  The 90 days runs from the time of the default termination or cancellation.  Or does it?  Look at what the ASBCA has said.

But first, look at the statute and the regulation.  FAR 33.211(a)(4)(v) requires a complete notification of appeal rights.  Requires.  A complete notification includes the right to appeal to the ASBCA within 90 days of the notification provided by the regulation (derived from the statute).

In 2017, the Board dismissed an appeal for lack of jurisdiction in which the contractor failed to file within 90 days of the notice of termination.  However, the Board did not examine whether the notification complied with FAR 33.211.  See Military Aircraft Parts, ASBCA No. 60139, February 21, 2017.  The only case cited by the Board to support its decision was the Board's prior decision in another Military Aircraft Parts case in which the notification complied with FAR 33.211.  Scratch your head.  The notification was defective in that it in no way complied with FAR 33.211.  Based on the Board's own precedent, the Board should have examined whether the contractor was prejudiced by the government's failure to comply with FAR 33.211.  The Board's inquiry would address what caused the failure to appeal within 90 days.

Importantly, in 2014, the Board denied the government's motion to dismiss an appeal filed after the 90 day deadline from the termination notice because the contractor was able to show it was prejudiced by a default notification which did not provide the contractor details about its rights to appeal to the ASBCA within 90 days (as required by FAR 33.211).  Mansoor International Development, ASBCA No. 58423, September 4, 2014.

In Mansoor, the Board based its decision on a 1996 Federal Circuit opinion.  The default notification merely said "Your company has the right to appeal under the disputes clause."  The Board found this was deficient, and, under the Federal Circuit authority, the contractor proved it was prejudiced by saying "[w]e did not understand our appeal rights and obligations and MiDs was prejudiced by the failure of the Contracting Officer in March to explicitly recite them."

In 2016, the Board decided a case in which the default notification informed the contractor of its right to appeal the determination under the disputes clause cited in FAR 33.211.  The Board found this notification was insufficient to start the running of the 90 days if the contractor could show it was prejudiced by the failure to be fully informed of its appeal rights.  The contractor made no attempt to show prejudice and the appeal was dismissed for lack of jurisdiction.  Bushra Company, ASBCA No. 59918, April 22, 2016,

The lesson is loud and clear.  Contractors, insist that any final decision include the appeal notification requirements in FAR 33.211.  Contracting officers, follow the requirements of FAR 33.211.  Finally, contractors, when in doubt, appeal within 90 days of any default termination.

Other precedent at the Board interprets contractor's communications liberally in deciding whether notice of appeal is effective.  A letter to the contracting officer may be enough if it adequately informs that the contractor intends to appeal or uses language indicating a dispute and request for relief.

Postscript:  If the T for D notice is defective because it does not comply with FAR 33.211, is the T for D not also defective and therefore a nullity which would result in conversion to a T for C?  Where a cure notice is required, the failure to provide one nullifies the T for D and results in conversion to a T for C.  Why not the same result for failure to comply with FAR 33.211?

bill@spriggsconsultingservices.com

Tuesday, May 28, 2019

USING OUR SEARCH TOOL

When you go to http://spriggslawgroup.BlogSpot.com, you will see our latest articles.  If you go to the upper left hand corner, you will find a search tool where you can do a word search of other articles.  We currently have posted over 200 articles on various federal government contract subjects.

bill@spriggsconsultingservices.com          bill@spriggslawgroup.com

Thursday, May 23, 2019

MISUSE OF DEFAULT TERMINATIONS REVISITED

On July 25, 2012, we warned of the misuse of terminations for default in connection with the government sequestration issue.  Lately, we've been concerned that the government may be misusing terminations for default in order to place the burden on the contractor to collect what it is owed when the government just wishes to abandon the contract for reasons other than a bona fide default by the contractor.  The government just wants to take the money off the contract for another use. 

Termination for default allows the government to move the funding off the contract. Conversely, funding must be left on the contract pending resolution of the termination for convenience settlement proposal.  Thus, the contracting officer has a funding motivation for turning the cancellation into a termination for default.

Termination for default is a drastic action which severely inhibits the contractor's ability to get new work with the government.  The law requires that it not be misused or abused. 

Termination for default shifts the burden of contract administration and all the contract risks to the contractor.  No termination contracting officer needs to be appointed and there is no administrative burden on the government.  There may be no reprocurement since the requirement is going away. The contractor must defend the termination for default action.

In defending the termination for default, it may take the contractor up to four (4) years of litigation to obtain a conversion of the termination to one for convenience which finally entitles the contractor to payment under the convenience termination clause.  We have seen many termination for default cases where the government has delayed the litigation for up to and sometimes longer than 4 years.

This is to say nothing of the expense of converting the default to a convenience termination and then going through the lengthy and expense process of collecting the convenience termination money.  We can think of no greater adverse action against increasing competition in government contracting than the misuse of terminations for default.

At the very least, the government should explore with the contractor, whether it may be possible to agree on a no cost termination for convenience settlement.  We suspect at least some of the drastic termination for default actions could be avoided by exploring this possibility.

bill@spriggsconsultingservices.com

Wednesday, May 15, 2019

CORRECTION OF CPARS RATINGS

The Armed Services Board of Contract Appeals (ASBCA) and Civilian Board of Contract Appeals (CBCA) have jurisdiction to decide whether the contracting officer acted reasonably in determining that performance was unsatisfactory or if such a CPARS rating was arbitrary and an abuse of discretion.  The Boards may decide whether the government acted arbitrarily and capriciously in making an inaccurate and unfair performance evaluation.  Cameron Bell Corporation d/b/a Gov Solutions Group (GovSG), ASBCA No. 61856, May 1, 2019.

The Boards also have jurisdiction to decide whether the government breached is implied by law duty of good faith and fair dealing when it assigned the CPARS rating.

The Boards do not have jurisdiction to grant specific performance (direct the contracting officer to change the CPARS rating) or grant injunctive relief.  The Boards cannot direct that the CPARS rating be changed.  However, the Boards may remand the matter to the contracting officer and require the contracting officer to follow applicable regulations and provide the contractor a fair and accurate performance evaluation.

So, it is possible to challenge a CPARS rating at the ASBCA.  The complaint must allege the contracting officer did not act reasonably and made an arbitrary determination which was an abuse of discretion.  The complaint also could allege breach of the obligation of good faith and fair dealing.  But the relief sought must be limited to requesting the Board to remand the matter to the contracting officer for a redo of the CPARS rating consistent with applicable regulations, fairness and accuracy.

bill@spriggslawgroup.com

Thursday, April 25, 2019

NOTICE REQUIREMENTS FOR REA'S AND CLAIMS

Often, the notice requirements in the Changes clause and the Differing Site Conditions clause are difficult if not impossible to meet.  Fortunately, a contractor may still be able to recover on requests for equitable adjustment (REA's) and claims depending on the close examination of the facts of each case.

As a general rule, the notice requirements should be observed and enforced.  However, as the law has developed, the exceptions to the rule have become the rule. 

If the government in fact knew or should have known the facts involved in the REA or claim, the contracting officer considered the claim without complaining about notice or the failure of the contractor to provide the notice did not materially prejudice the government, the notice requirement will not be enforced.  Government records may show knowledge or the presence of government representatives at the site and their assistance in the attempts to solve the problem may also show knowledge of the issues.

The purpose of the notice clauses is to be sure that government knows of problems so it can act to solve them to its satisfaction.  However, if there is no prejudice to the government in that it is not materially harmed by the failure of prompt notice, the notice requirement will not be enforced.

The same rules apply to the Differing Site Conditions clause notice requirements.  The purpose of the notice requirement is to give the government the chance to change the design or construction and to mitigate its costs.  Unless the lack of notice results in actual prejudice, the government's defense of lack of notice will be rejected.

Perhaps most importantly, notice requirements to not apply to breach and constructive changes claims.

bill@spriggsconsultingservices.com

Friday, April 19, 2019

THE RULES ON DISCLAIMER CLAUSES

The government often disclaims responsibility and shifts risks to contractors through various disclaimer clauses. As a consequence, contractors often find themselves unable to obtain relief when they encounter conditions giving rise to claims for additional compensation.  They lose their case based on the government's defense that the risk of extra costs was shifted to the contractor through a disclaimer clause.  So just what are the rules governing the interpretation and enforcement of so called disclaimer clauses?

First, the government may assign a specific risk to a contractor even if such an assignment is ridiculous and should never be accepted by the contractor.  If clearly stated, a contract may shift the risk to a contractor "to make snowmen in August."  Rixon Electronics, Inc. v. United States, 536 F.2d 1345, 1351 (Ct. Cl. 1976). 

However, when the contract clause merely says information in the solicitation may be inaccurate, the clause does not transfer the risk to the contractor.  Metcalf Construction Co. v. United States, 742 F.3d 984, 988, 995-96 (Fed. Cir. 2014).  If there is not clear language alerting the contractor that it should bear the risk, the disclaimer clause probably will not be enforced.

Second, contractors are responsible for making a reasonable pre-proposal site visit.  The rule is that if a reasonable contractor would have noticed the problem, the risk shifts to the contractor.  However, the duty to make a reasonable inspection of the site does not require the contractor to discover conditions "beyond the limits of an inspection appropriate to the time available."  Foster Constr. C.A, and Williams Bros. Co. v. United States, 435 F.2d 873, 888 (Ct. Cl. 1970). 

The whole idea is that the contractor has only a limited time to prepare its proposal and is bound by the disclaimer clause only to the extent he has a reasonable time to assess the cost of the problem.  The more specific the clause, the more obvious the problem and the more time to assess, the more likely the disclaimer clause will be enforced.

For the rules on interpretation of contract language generally, see our articles on contract interpretation by using the search tool in the upper left hand corner.  Insert these words: contract interpretation.

bill@spriggsconsultingservices.com

Wednesday, April 17, 2019

PROTESTING CORRECTIVE ACTION

Yes, you can challenge corrective action through a protest at the GAO.  NavQSys, LLC, B-417028.3, March 27, 2019.

Although corrective action is within the discretion of the contracting agency and GAO will not object to specific corrective action provided it is an appropriate remedy, GAO will sustain a protest if the agency's decision is inconsistent with the solicitation or is otherwise unreasonable.

Importantly, the agency must document its decision and preserve the materials upon which it is based so that GAO may review the action.

In this case, the agency determined it would terminate the awarded contract for its convenience and make the award to a competitor.  When the contractor to which the contract originally had been awarded protested, GAO examined the record to see what justified the agency's decision.  As it turned out, there was nothing in the record to show the agency's decision to terminate the award was justified.  The agency failed to provide a clear explanation of its action.

The case stands for the proposition that GAO will sustain a protest where the record fails to provide GAO with an opportunity to review in a meaningful way whether the agency's decision was reasonable.

Of course, a protester must show prejudice in order to prevail.  On this point, GAO resolved any doubt in favor of the protester since a reasonable possibility of prejudice is a sufficient basis for sustaining a protest.

Unfortunately, the remedy GAO provided was hardly a victory for the protester.  GAO's recommendation to the agency was that it document the basis for its decision to reject the proposal submitted by the protester.  We see a follow up protest coming.

bill@spriggsconsultingservices.com 

Friday, March 29, 2019

READ THE EVALUATION FACTORS!


What is the first thing you should do when you get a solicitation for a competitive government buy?  Find the evaluation factors, read them, make sure you understand them, make sure they are fair, make sure they comply with the regulations and use them to manage your proposal effort.  If they are not clear, fair or if they do not comport with the regulations, protest immediately.  We can assure you most problems in competitive procurements are caused by improperly articulated evaluation factors.  The time to solve these problems is when the solicitation is first issued.

We are against protesting unless a regulation is violated.  We also are against writing stuff people do not understand.  If the evaluation factors are not written clearly and if they do not strictly follow regulatory requirements, protesting is an absolute necessity.  This is probably the one situation where there is no doubt about the propriety of protesting all the way up the line.  First, “protest” to the contracting officer.  Write a letter (emails are legal letters) thoroughly explaining what is unclear or illegal about the evaluation factor section of the solicitation.  Yes, it is illegal to fail to follow the regulation on evaluation factors.  If that doesn’t work, file a formal agency protest or protest to GAO.

Evaluation factors are discussed In FAR Parts 12, 13, 14 and 15.  All competitive procurements implicate FAR Part 15 principles, according to GAO.  Part 15 has the most thorough discussion of evaluation factors.  Although Parts 12, 13 and 14 have their own discussions and Parts 12 and 13 allow much more discretion as to what factors are used, Part 15 is the gospel on evaluation factors.  The main point to remember is that all competitive procurements require a solicitation contain evaluation factors.  They must also be written in plain English. 

If nothing else, failure to state evaluation factors is egregiously unfair.  How in the world can you compete if you don’t know how you will be judged?  Why would you engage in any competition without knowing the rules of the game?