The Spriggs Law Group practices federal procurement law before all federal agencies and tribunals. Claims, protests, disputes and appeals.
Monday, October 30, 2023
Monday, October 23, 2023
A GUIDE TO PROFITABILITY OF CHANGED WORK
Many, if not most, contractors have been smart enough to build the effects of inflation into their initial pricing on government contracts. Some of them, however, did not get it exactly right. And then some did not price the risk of extraordinary inflation for one reason or another. We are here to sympathize with those of you who are being killed by inflation, which you did not reasonably expect to help you recover from the impact of inflation, and show you how you can be made whole on your contract. Our approach to making the contractor whole is based on the words used by the appellate court in 1963 to describe the objective regarding remuneration on a contract that has been changed. In describing the process by which contractors are compensated when there are changes, the court, referring to the mechanism of an equitable adjustment, stated:
“Equitable adjustments in this context are simply
corrective measures utilized to keep a contractor whole when the Government
modifies a contract. Since the purpose underlying such adjustments is to
safeguard the contractor against increased costs engendered by the
modification, it appears patent that the measure of damages cannot be the value
received by the Government but must be more closely related to and contingent
upon the altered position in which the contractor finds himself by reason of
the modification.” Bruce Construction
Corporation v. United States, 324 F.2d 516 (Ct. Cl. 1963).
This is not your definitive treatise on recovery
of damages for breaches of construction contracts in the private sector. Here, we address those contractors who also deal in the public sector and are
concerned about sufficient recovery in the event of changes and how to make
contracts attractively profitable. Stated another way, some contractors are
wary of or even leaving the public sector based on their perception of
stringent restrictions on recovering damages if things go wrong. They may primarily
be concerned about the effects of inflation and what to do about it because
much has been written about how there are no clauses in public contracts that
protect contractors from inflation. And that is correct except for limited
assistance by the DOD.
In private contracting, damages fall roughly into
three categories: direct, incidental, and consequential.
In public contracting, damage calculations are
made in the context of the changes clause, which provides an equitable adjustment.
That concept was articulated in Bruce to mean that the contractor should
be made whole. The idea of making the contractor whole has been the basis for
the development of the law on the meaning of equitable adjustment.
Traditionally, equitable adjustment includes the direct cost of performing
change, the indirect associated costs, and the profit on those costs. It is
important to note that actual costs are required, although estimates are
permitted. In addition, the direct and incidental costs associated with the
change are included in an equitable adjustment. However, the changes clause
itself contemplates the recognition of consequential damages. The requirement
to make the contractor whole is embodied in the notion that the change may
affect the original work.
Early in the development of the law of federal
government contracts, it became evident that the concept of equitable
adjustment could well include the impact of the change on the unchanged work. Therefore,
the changes clause was amended to include “whether or not changed”, meaning
that increased cost could be recovered on the original work. So-called delay and disruption costs
traditionally have been included in the equitable adjustment calculation
because of this language in the changes clause permitting the impact on
unchanged work.
But when the Court of Appeals for the Federal
Circuit decided an equitable judgment was to make the contractor whole, what
did that concept include? How far does it go? Making a contractor whole is more
than just remuneration. For one thing, it's been well recognized that the concept
includes reevaluating profit on the costs. Profit, arguably, is correctly
increased in the calculation to account for the fact that changed work is
uncertain and requires greater risk and, presumably, the prospect of greater
rewards. Not enough attention has been paid to the calculation of profit. The
Armed Services Board of Contract Appeals has permitted 13% profit on changed
work on a shipbuilding claim. The 10% profit often used as a benchmark should
be increased to at least 13%.
It is not far-fetched to suggest that the concept
of equitable adjustment, as interpreted by the Court of Appeals for the Federal
Circuit, should include elements that would make the contractor whole, such as non-remunerative.
The delay permits the calculation of costs but also implicates the design and
performance aspects of the contract. The effect of the change on the unchanged
or original work could well include a need to redesign the structure or item of
equipment. Likewise, the original work may well be affected by the change to
the extent that the means and methods of performance of the contract need to be
changed, making them entirely different than originally planned. Manpower may
be necessary to be replaced with workers with different expertise. Certain
aspects of the project may have to be demobilized, and others mobilized. So,
it's not just the costs of the impact on the unchanged work that are
recoverable. The concept of making the contractor whole could include
restructuring the project and its management.
In public contracting, it's the government's job
to scrutinize the contractors’ claims to be sure that the contractor is not
carrying the concept of making itself whole to the extreme. The same applies to
the private sector, where the owner must scrutinize the contractor’s damage
claim. Contractors
articulate their entitlement and then throw in the kitchen on damages. Folks
often misinterpret the entitlement side to justify throwing every damaged item
they can think of against the wall to see what sticks. They hold to the concept
that if you do not ask for it, you will never have a chance to get it.
It is difficult to fault the contractor for being
aggressive. The concept of being made
whole seems to support their position.
It is possible to reprice all original work affected by the change and,
in the process, lessen the effects of inflation.
Sunday, October 22, 2023
LEADERSHIP
You arrive 10 minutes late to the 4 o'clock meeting and sit at the head of the table or stand at the podium. You launch into an expression of your views on the agenda subjects. You refer to policies and practices you exhort everyone to follow.
You purposely avoid any indication things are going well because that only encourages people to expect bonuses. You thank everyone tersely, ask if they have any questions, and then leave the room. You worked hard to get to your leadership position, and are proud of how smoothly the meeting went.
Leadership? That is not leadership.
Why have a meeting? There are only two reasons: 1) congratulate or compliment others, or 2) listen to others. Either announce public praise or learn from all those people you hired to do their best. You speak last about what you've learned and not about you.
In my advice to CEOs based on my 37 years as a CEO and a Marine Corps officer before that, they, not you, come first. And you mean it; demonstrate it. You do not wait, half listen, then take the stage and announce your conclusions and directions.
Be vigilant. You agree with the universal truth of praise in public and criticize in private. But there are other truths. Listen. You are supposed to be the smartest one in the room. But you are not. You are the lucky leader.
Get to the meeting early. Do not sit at the head of the table or stand at the podium. Encourage candor. Find ways to express your empathy. You need them more than they need you. Yes. Let that sink in. In attitude, you work for them.
HOW TO WRITE A MONETARY CLAIM
1.
Send a letter to the contracting officer which claims
relief in simple, concise terms. Follow instructions on how to write a request for equitable adjustment but call it a claim. State fats and legal theories of recovery.
2.
The letter says it is a claim pursuant to the Contract
Disputes Act of 1978 and FAR Parts 2.101 and 33.201 through 214.
3.
In the letter, state that you request a final decision
of the contracting officer as required by the Contract Disputes Act of 1978 and
FAR 33.211.
4.
Certify the claim (if it exceeds $100,000.00) as
follows: I certify that the claim is
made in good faith, that the supporting data are accurate and complete to the
best of my knowledge and belief; that the amount requested accurately reflects
the contract adjustment for which the contractor believes the government is
liable; and that I am duly authorized to certify the claim on behalf of the
contractor. Do not deviate from this
language found in FAR 33.207(c).
5.
Be sure to state a sum certain as the claim amount.
6.
Point out that interest runs on the claim from the time
of its receipt. FAR 33.208.
7.
Be sure to request a final decision as required by FAR
33.211.
8.
Appeal the decision (or the failure to render one) to
the appropriate Board.
Saturday, October 21, 2023
PROMPT JUDICIAL INTERVENTION
Why declaratory relief? It can break up an impasse preventing performance. What is it? A judgment from the court or board that resolves a dispute that may be a severe impediment to continued performance.
Suppose you are managing your federal government contract as we have suggested. In that case, you will have a relationship with the contracting officer that promotes transparent, well-documented negotiation of solutions to performance problems. (One of my clients once told me he was unsure who his contracting officer was.)
The fastest, most effective way to resolve disputes is one-on-one, perhaps even while washing up in the restroom (remind me to tell you that story). Know, be very friendly with, and respect your warranted contracting officer. Communicate daily.
If you have an unresolvable disagreement, get her agreement to ask for an ADR judge to mediate. Both Boards will dispatch a real judge to aid as a neutral at any stage of your problem, even early claim and incipient dispute. And why not? The judges have been trained to unite the parties; they are highly motivated, and it does not cost anything. One day should do it. It's not a trial.
Then, there is the point of this piece. The Civilian Board just issued a decision denying the contractor's request for declaratory relief on a nonmonetary claim. The attorney involved is an old salt who should have known better. One longstanding test for such relief is whether there is an adequate legal remedy. Clearly, a monetary claim was adequate relief. Declaratory relief is an extraordinary equitable remedy where there is a dispute that the declaration will resolve and legal remedies are unavailable.
Let me repeat for emphasis. To obtain declaratory relief on a timely basis, there must be a genuine dispute, an action by the court or board can resolve it, and no remedy at law is available to resolve the dispute. The best example is a disagreement over the interpretation of language in the contract.
The best example is a contract interpretation issue, a legal matter solely within the province of the court or board. The parties are at an impasse, and performance cannot reasonably continue without judicial intervention.
In our experience, 90% of serious disputes involve contract interpretation issues, and the situation cries out for prompt determination by a judge. File your nonmonetary claim. No certification. No 60-day wait for a final decision.
We've been successful with this. The contractor and the contracting officer were at an impasse over language in the contract. The contractor thought its obligation was over when the warranty period expired. The government took the position the warranty began to run once the total construction phase was tested and accepted. The contractor wanted to refuse to perform. Instead, we filed a declaratory relief action to force the contract interpretation issue and whether the order to perform was a cardinal change. We settled the case with the help of the board judge.
Wednesday, October 18, 2023
SUBCONTRACT DISPUTES CLAUSE
(a) Any dispute that arises under or is related to this
Agreement and which relates to a matter that gives the Prime Contractor
recourse against the U.S. Government under the Prime Contract or applicable law
shall be resolved in accordance with the Disputes clause of the prime contract
as follows:
(1) Subcontractor will give Prime Contractor a fully
supported written claim concerning any such dispute within five (5) years after
the claim accrues, but in no event later than final payment under this Agreement,
or Subcontractor shall be barred from any remedy for such claim.
(2) Subcontractor will cooperate fully with Prime Contractor
in prosecuting any such dispute and will be bound by the outcome unless: (i)
Prime Contractor does not afford Subcontractor a reasonable opportunity to participate
in the resolution of the dispute, (ii) without Subcontractor's written consent,
Prime Contractor settles or takes other action to prejudice Subcontractor's
rights concerning the dispute, or (iii) Prime Contractor, having determined to
discontinue its own prosecution of the dispute, does not afford Subcontractor
an opportunity to continue to prosecute the dispute in Prime Contractor's name;
(3) If Prime Contractor and Subcontractor agree to prosecute
Subcontractor's claim under this subparagraph (a), for any such claim for more
than $100,000, Subcontractor shall submit with the claim a certification to
Prime Contractor and to the contracting officer for the prime contract, signed
by an authorized representative of the Subcontractor that: (i) the claim is
made in good faith; (ii) the supporting data are accurate and complete to the
best of the signatory's knowledge and belief; (iii) the amount requested
accurately reflects the contract adjustment for which Subcontractor believes
the U.S. Government is liable; and (iv) the signatory is duly authorized to
certify the claim on behalf of Subcontractor. Furthermore, Subcontractor shall
indemnify and hold Prime Contractor harmless from damages, judgments,
(including reasonable attorney's fees), and other liabilities arising from any breach
of such certification or any violation of Section 5 of the Contracts Disputes
Act of 1978 (4I U.S.C. 604) or any violation of costs common law or statutory
prohibitions against misrepresentations, fraud or false statements;
(4) Prime Contractor and Subcontractor will each bear their
own costs of prosecuting any such dispute;
(5) If the parties do not agree to proceed in accordance
with this paragraph (a), the dispute will be decided in accordance with
subparagraph (b) hereof;
(6) Nothing in this Agreement Grants Subcontractor a direct
right of action against the United States under the Disputes clause of the
prime contract, except insofar as certain intellectual property clauses flowed
down from the prime contract may so state or be construed to so provide.
(b) Any other dispute that arises under or is related to this
Agreement, as well as any dispute that the parties to do agree to resolve
according to the procedures set forth in the foregoing subparagraph (a), may be
decided by a court of competent agree that jurisdiction and venue lies
exclusively in the courts of the Commonwealth of Virginia.
(c) The Subcontractor shall proceed diligently with the performance
of this Agreement, pending final resolution of any request for relief, claim,
appeal, or action arising under or relating to the Agreement.
HOW TO PRICE A REQUEST FOR EQUITABLE ADJUSTMENT
1.
DIRECT MATERIAL
2. DIRECT LABOR
3.
INDIRECT FACTORY
OR FIELD OVERHEAD EXPENSE,
IF APPLICABLE
4.
SUBCONTRACTOR REA COSTS
AND SUBCONTRACTOR'S PROFIT ON THOSE
COSTS
5. COSTS OF CONTRACT ADMINISTRATION IN DEALING WITH CHANGE, INCLUDING REA PREPARATION AND NEGOTIATION COSTS (BE SURE TO REMOVE FROM G & A POOL WHEN CHARGING DIRECT)
6. DELAY AND DISRUPTION COSTS, INCLUDING LABOR INEFFICIENCY, MATERIAL AND LABOR COST/RATE INCREASES, AND UNABSORBED HOME OFFICE OVERHEAD
7.
ANY
ADDITIONAL COSTS OF THE EFFECT OF THE CHANGE ON THE
UNCHANGED ORIGINAL WORK, INCLUDING
EFFECTS OF INFLATION,
CHANGES TO MEANS AND METHODS OF PERFORMANCE, CHANGES TO DESIGN, CHANGES TO
SCOPE OF WORK.
8.
GENERAL AND ADMINISTRATIVE EXPENSES ON ALL REA COSTS
9.
PROFIT ON ALL COSTS (USUALLY AT 12% FOR
CHANGED WORK)
A WALK THROUGH FAR (BUT NOT TOO FAR)
You all are familiar with the Federal Acquisition Regulation (FAR). However, you may need a handy reference guide to the various Parts and Subparts. I’ve put together a summary of the Parts with comments based on my experience over more than 40 years of using FAR. My comments obviously are based on my experiences and my notes reflect my opinions on the relative importance of the various Parts. I think you will find, however, that my suggestions on which Parts merit close attention and careful reading are universally true.
Each numbered paragraph corresponds to a FAR Part. (H) means highly important, (M) means only
sometimes important, and (L) means seldom important.
1.
(M)
States guiding principles, how regulations are arranged, circumstances
under which regulations, clauses, policies, and procedures may deviate from the
FAR rules, and generally how to prepare a D & F (Determination and
Finding).
2.
(H)
Definitions. Always check to see
if the word you are focused on is defined in Part 2.
3.
(H)
Improper Business Practices and Personal Conflicts of Interest
section. Whistleblower protection for
contractor employees and contractor code of business ethics and conduct. Procurement integrity prohibitions,
restrictions, and requirements.
4.
(M)
Various administrative matters such as contract execution, distribution,
contract reporting, contractor records retention, CCR, Reps, and Certs, and
reporting contractor compensation and first-tier awards.
5.
(M)
Publicizing contract actions.
Methods of dissemination of information and how and when to synopsize
contract actions.
6.
(H) Full
and open competition is required except in certain stated circumstances. Exceptions must be fully justified.
7.
(H)
Acquisition Planning including policy on contractor versus government
performance. Rules on the content of
written acquisition plans. Detailed
discussion of “inherently governmental functions”.
8.
(H)
Required sources of supplies and services. Subpart 8.4 is the only FAR discussion of
Federal Supply Schedules.
9.
(H)
Contractor qualifications, including rules on contractor responsibility,
qualifications, debarment, suspension, and ineligibility, and an important
section on organizational and consultant conflicts of interest (subpart 9.5).
10.
(M)
Market research requirements.
11.
(L) Seldom
an issue. Describes agency needs
including liquidated damages, priorities and allocations, and variation in
quantity.
12.
(H)
Acquisition of commercial items.
This is being used a lot.
Different rules for changes and terminations. Reduced number of clauses. Streamlined procedures. This is a good time to check the definition
of commercial items in Part 2.
13.
(M) Simplified
acquisition procedures. See the definition
of simplified acquisition threshold in Part 2.
14.
(M)
Sealed bidding rules. Seldom
used. Hardly ever used for services.
15.
(H)
Extremely important. All the
rules on negotiated acquisitions. Read
carefully. Contains rules on how
solicitations are to be put together, what they should include, how the
evaluation factors are to be written, how to conduct discussions and source
selection, make awards, notify winners and losers, and how to conduct
debriefings. Subpart 15.4 contains all
the rules on contract pricing. The
section ends with a discussion of unsolicited proposals which is very important
but often overlooked. In these days in
which the government is crying for innovation, 15.6 becomes very important.
16.
(H)
Discussion of all the various types of contracts. Must-read.
A complete discussion of fixed prices, IDIQ, and T & M.
17.
(M)
Multi-year contracting, options, and interagency acquisitions.
18.
(L)
Emergency acquisitions.
19.
(H)
Extremely important. All the
rules on small business programs including policies, set-asides, certificates
of competency and determinations of responsibility, contracting with SBA (8a),
and HUBZone rules.
20.
Reserved.
No content.
21.
Reserved.
No content.
22.
(M) All
about labor laws including Walsh-Healey, Service Contract Act, and disabled
veterans.
23.
(M) Rules
in the environment, energy and water efficiency, renewable energy technologies,
occupational safety, and drug-free workplace.
24.
(M)
Protection of privacy and freedom of information.
25.
(M)
Foreign acquisition. Buy American
Act, trade agreements, and prohibited sources.
26.
(M) Other
socioeconomic programs including preferences for disaster or emergency
assistance, and Indian-owned and historically black institutions.
27.
(H)
Patents, Data, and Copyrights. An
extremely important section on Rights in Data.
28.
(L) Bonds
and insurance.
29.
(L)
Taxes.
30.
(M) Cost
Accounting Standards. No worry for small
businesses.
31.
(H) An
extremely important section on allowable costs.
The five tests of allowable costs.
Worth reading.
32.
(H)
Contract financing including progress payments, contract debts, contract
funding, prompt payment, and electronic funds transfer.
33.
(H) All
the rules on protests, disputes, and appeals.
A must-read for protests and disputes.
34.
(L) Major
System Acquisition.
35.
(M)
Research and development contracting.
36.
(M)
Construction and architect-engineer contracts.
37.
(M)
Service contracting. Not really
much meat here.
38.
(M)
Federal Supply Schedule contracting.
Basically refers back to 8.4.
39.
(M) Acquisition of information technology. Not really much meat here either.
40.
Reserved.
No content.
41.
(L)
Acquisition of utility services.
42.
(H)
Contract administration and audit.
Rules for contracting officers.
Important section on novations and change of name agreements. Extremely important in light of the
anti-assignment statutes.
43.
(M)
Contract modifications. Change
orders.
44.
(M)
Subcontracting policies and procedures.
Not much meat.
45.
(M)
Government property use, title, reporting, and disposal.
46.
(M)
Quality assurance. Contract
clauses, government, and contractor responsibilities.
47.
(L)
Transportation.
48.
(L) Value
engineering. Hardly used.
49.
(H)
Termination of contracts.
Extremely important to read thoroughly.
Covers both terminations for default and for convenience. 49.201 is a thing of beauty. Cure notice and show cause notice
discussed. Adjustment for loss.
50.
(L)
Extraordinary contractual actions and the Safety Act. Hardship relief. Support anti-terrorism by Fostering Effective
Technologies Act of 2002.
51.
(L) Use
of government sources by contractors.
52.
(H) All
the solicitation provisions and contract clauses. 52.3 contains a matrix that tells you which
clauses for which type contracts are required or optional. But there is nothing in FAR telling you which
clauses are mandatory subcontract flow down clauses.
53.
(H) All
the prescribed forms with illustrations.
HOW TO WRITE A REQUEST FOR EQUITABLE ADJUSTMENT
1. The
change proposal narrative containing:
(a) Summary statement of the change.
(b) Statement of the contract requirement.
(c) Statement of the Government direction or
actions or inactions that caused the contractor to exceed the contract
requirements.
(d) Detailed statements of the added work or
work performed exceeding contract requirements.
(e) Computation of the costs of work
exceeding contract requirements.
(f) (A Legal brief may be included in each
claim package or group of packages as the circumstances indicate.)
2. An
indexed and tabbed appendix containing, as applicable.
(a) Excerpts from pertinent contract
documents.
(b) Pertinent contract drawings.
(c) Pertinent correspondence and performance
documents.
(d) Charts and tables containing or analyzing
data.
(e) Photographs.
(f) Technical write-ups.
(g) Excerpts from technical treatises.
(h) Expert opinions.
(i) Cost computation.
(j) Any other pertinent documents or data.
(k) (Additional extremely detailed supporting
material of a bulky nature should be readily retrievable but not necessarily
appended to the change proposal.)
Each of the foregoing items of documentation for
the change proposal is described briefly below.
1(a). Summary. As the name implies, the summary statement is
a brief statement of the claim. It
should be complete including the amount claimed. However, it should never
consist of more than several short paragraphs.
Its purpose is to inform the reader of what he will learn if he reads
the rest of the change package. It is
important that the summary be accurate.
The summary should normally be prepared after all other writings, as set
out below, is completed.
1(b). Contract
Requirements. Since costs are being
claimed for exceeding contract requirements, it is essential that the original
contract requirements be clearly established at the beginning of the change
proposal. This is accomplished by
stating the contractor's interpretation of the contract requirement and then
proving it to be reasonable by reference to each and all of the specification
paragraphs, drawings or other contract documents upon which reliance is placed
for that particular interpretation. This
is the baseline that must be established. To avoid excess length in the
narrative, it frequently is desirable to include reproductions of contract
articles in the appendix, to which reference may be made. See Paragraphs
2(a), and (b) below.
1(c) The
Change. This is the paragraph that
will present some or the greatest difficulties in preparing, i.e., tying
performance exceeding contract requirements to the Government's action or
inaction (including issuance of defective or impossible drawings and
specifications). Where there is a
written document directing the contractor to do or not to do certain work (even
though not a formal change order), the problem is made easy. Where there was a document prepared rejecting
work considered to fulfill contract requirements, the problem is made
relatively easy. Likewise, where there
was a defect or incompatibility in the contract's drawings or specifications,
identification of the “constructive change” is relatively easy. However, it is not at all unusual for the
major portion of changes to arise from circumstances where the Government
gently nudged a contractor into a particular course of action. Some or all of the “nudges” may have been
oral, instead of written. The direction
in such areas is not direct but is more subtle.
For claim purposes it is necessary only that the government has participated
in the decision or the event that resulted in the contractor proceeding in a
certain manner.
It is particularly in this area of investigation
that the perception of the claim writers and investigators must be
exercised. For example, if difficulties
are encountered with the item to be manufactured, it may be because the
government changed the item's configuration (perhaps by work rejection) sometime
earlier. Similarly, for example, the claim investigators may not readily see
how a certain construction method or sequence was directed by the
Government. However, the reason for the
construction technique may have been the lack of trained personnel to do it in
another manner. The lack of trained
personnel in turn may have resulted from some direction that absorbed the
available skills in this area. In other
words, changes must be traced to their ultimate origin and at times one must
look behind the obvious and proximate causes for the real cause.
1(d). The
Added Work. The Government cannot
pay for work exceeding the contract requirements unless it knows precisely and
in detail what that excess work is.
Accordingly, it is necessary to describe by size, weight, length,
increased performance, etc., whatever it is that is being asserted as extra
work. Such description cannot be vague
or general, it must be specific.
Where the change is based upon a defect or incompatibility in the
drawings and specifications, a delay, a change of sequence, a redesign of work
or over-inspection, etc., the resulting extra work must be described with
particularity. It is not sufficient to
simply say that certain work was "delayed" or there was "impact."
The method by which the changes are quantified, i.e.,
the number of times an item was reworked, the number of drawing revisions, the
number of man hours and materials lost through a change or defect in drawings,
the increased quantities of materials used, etc., must be stated. This statement ties in with the cost
computation (1(e). below and it is not necessary to duplicate the quantities in
both sections. The purpose of the
present section is to make it clear that the change is for a certain quantity
of material, and/or labor, and/or delay, etc., and is not a change for
something else or something which cannot be quantified.
1(e). Cost
Computation. The computation of costs for the additional work is
principally the job of the accountants, change order estimators and cost
analysts. However, the claim writers and
investigators will contribute a major input in identifying quantities as
discussed in 1(d) above. In addition,
much of the pricing will be based upon engineering estimates which must be made
by the original investigating group.
1(f). Legal
Brief. A legal brief, if
appropriate, will be prepared by the attorneys who also will review and revise,
if necessary, the other sections of the change proposal narrative to coordinate
legal theory with provable fact.
Appendices
2(a). Contract. The use of contract excerpts is discussed in
Paragraph 1(b) above. Such excerpts
should be complete for this particular change proposal so that the parties
reviewing the claim need not go back to the contract itself.
2(b). Drawings. Same as 2(a) above.
2(c). Correspondence. These are documents generated during
performance and usually are included in the appendix to support the statements
in Paragraphs 1(c) and (d)., the work performed, and the Government's direction
to perform such work. Typically they may
include correspondence, minutes of meetings, test reports, but may consist of
any type of document. If they support
the claim and are not too bulky, include them in the appendix.
2(d). Chart
and Tables. Frequently raw data is
too voluminous to include in an appendix.
It should be charted, scheduled, tabulated, made into overlays, etc., in
such a manner as to support the claim.
It is extremely important that any such chart specifically reference the
source of the raw data and its retrievable location. Use of this type of material should be
maximized.
2(e). Photographs. "A picture is worth a thousand
words" is a saying that has particular applicability to proving
facts. Typically it not only proves the
fact of the change, but also is descriptive of what the change is. On the other hand photographs are dangerous
because they may show something inconsistent with a position asserted in some
other change proposal. They are
valuable, but use with caution.
2(g). Technical
Write-ups. Changes (and defective
specifications) frequently are based upon highly technical considerations. Frequently because of the length of the
necessary technical discussion, it is undesirable to include them in the change
proposal narrative and thus break the continuity and persuasiveness of the
narrative. Accordingly, it may be
desirable to summarize the technical discussion in the narrative and to present
it in complete detail in the appendix.
2(g). Technical
Treatises. Where technical
consideration are involved, it may be desirable to reproduce a few pages or a
chapter of an accepted technical treatise that supports the positions advanced.
2(h). Expert
Opinions. An expert opinion may be attached under the same consideration
discussed in 2(g) above.
2(i). Cost
Computation. Normally the narrative
(See 1(e). above) will contain only a summary of the cost
computation. Detail should be included
in the appendix. There will be another
layer of detail and raw data, work papers, etc., which will be available but
will not be included in the appendix and should be clearly referenced therein.
2(j). Other
Data. The above listing of
supporting documentation is not intended to be all inclusive and any other
material which may be considered persuasive should be included in the appendix.
The nature of appropriate material is
limited only by the nature of the material available and the imagination and
ingenuity of the people preparing the change proposal. Remember that after claim identification and
investigation, the major job becomes salesmanship. The first element of salesmanship is clear
statement of the change.
2(k). Bulky
Data. It is both impossible and
undesirable to include all supporting data in the appendix because of bulk and
also because much of it is of a lower tier evidentiary value. However, it should be identified, catalogued,
and available for presentation to the government should it request it or should
the circumstances later indicate the desirability of it being submitted. Much of the lower tier material would be
presented at a contract appeal hearing before the Armed Services Board of
Contract Appeals.
HOW TO WRITE A SPONSORSHIP AGREEMENT
Subcontractor will give Contractor a fully supported written REA within five (5) years after the REA accrues but in no event later than final payment under this Agreement or Subcontractor shall be barred from any remedy for such REA.
Subcontractor will cooperate fully with the Contractor in
prosecuting the REA against the Owner and will be bound by the outcome unless the Contractor does not afford the Subcontractor a reasonable opportunity to
participate in the resolution of the REA or Contractor, having determined to
discontinue its own prosecution of the REA, does not afford Subcontractor a chance to continue to prosecute the REA in Contractor’s name.
The contractor shall cooperate with the Subcontractor in
prosecuting the REA against the Owner. Still, the Contractor shall have the sole right
to make final decisions on prosecution and settlement of the REA. The subcontractor will take the lead in
prosecuting the REA against the Owner, and the Contractor will assist the Subcontractor
by allowing the Subcontractor to pursue the REA in the Contractor’s name.
Subcontractor shall submit with the REA a certification
to Contractor, signed by an authorized representative of the Subcontractor, that
the claim is made in good faith, the supporting dates are accurate and complete
to the best of the signatory’s knowledge and belief, the amount requested
accurately reflects the contract adjustment for which Subcontractor believes
the U.S. Government is liable. The signatory is authorized to certify the
REA on behalf of the Subcontractor.
Subcontractor indemnifies and holds the Contractor harmless from damages,
costs (including attorney fees), and other liabilities arising from any breach
of such certification or any violation of the law against misrepresentation, fraud, or false statements.
Contractor and Subcontractor will each bear its own costs
of prosecuting the REA.
The subcontractor shall proceed diligently with performance
of this Agreement pending the final resolution of any REA arising under this
agreement.
This clause applies to any REA, claim, or appeal arising
under or related to this subcontract agreement.
HOW TO WRITE A CLAIM
1.
Send a letter to the contracting officer which claims
relief in simple, concise terms.
2.
In the letter say, it is a claim under the
Contract Disputes Act of 1978 and FAR Parts 2.101 and 33.201 through 214.
3.
In the letter, state that you request a final decision
of the contracting officer as required by the Contract Disputes Act of 1978 and
FAR 33.211.
4.
Certify the claim (if it exceeds $100,000.00) as
follows: I certify that the claim is
made in good faith, that the supporting data are accurate and complete to the
best of my knowledge and belief; that the amount requested accurately reflects
the contract adjustment for which the contractor believes the government is
liable; and that I am duly authorized to certify the claim on behalf of the
contractor. Do not deviate from this
language found in FAR 33.207(c).
5.
Be sure to state a sum certain as the claim amount.
6.
Point out that interest runs on the claim from the time
of its receipt. FAR 33.208.
7.
Be sure to request a final decision as required by FAR
33.211.
8.
Appeal the decision (or the failure to render one) to
the appropriate Board.
Tuesday, October 17, 2023
AN OPEN LETTER TO GENERAL MARK MILLEY
You are our Dwight David Eisenhower man of the hour. We have seen your speech upon leaving office. We have observed your testimony before Congress. We have watched your distinguished military career. You are intelligent and strong and speak for us as you are profoundly empathetic.
You have spent your life in service for us. We are deeply grateful. But we desperately need you to continue that service to support democracy and against minority rule and would-be dictators.
We entreat you to lead your colleagues in the military-industrial establishment to speak out orally and in writing in support of democracy and against the uprising of fascism. Write an open letter to the American people. Repeat what you already have said. Repeat the oath and what it says and means.
You are our statesman. Our only one. Please continue to serve us. The only coalition powerful enough to stop the Trump cult is the military-industrial voice of reason, reminder, and redemption.
Your time in history is upon us, and you have prepared yourself well. Muster the troops. Be there for us.
Saturday, October 14, 2023
ALERT: THE WANNABE DICTATOR . . .A CLARION CALL FOR ACTION
General Milley chose his words wisely. In a strong commander's voice, he warned of the election of the wannabe dictator. We all heard him. Yet there is no sign of a plan to heed the warning. The 14th Amendment won't stop him (the Supreme Catholic Court). Losing the popular vote won't stop him. Barrels of money and bombardments of ads won't stop him. Congress can't, and the elitist (Mark Warner) Democrats are bereft of fresh ideas.
I have proposed the military-industrial complex leaders sign an open letter to all Americans supporting democracy and the Constitution and condemning wannabe dictators.
The subtleties will pass by half the electorate unrecognized but will influence them to consider whether to continue the insurrection. The most potent force in the world has spoken against the existing minority rule and the incipient rise of autocracy/theocracy.
I can't believe I must write this and that my friends and fellow Americans give me no support. I predict the wannabe dictator will win. Who are you, you say. Why should we heed your call? So you don't know or like me. That does not mean I should be ignored. I just study the evidence.
All I'm asking is that you join me in contacting leaders of the military-industrial establishment and entreat them to sign the open letter that supports democracy, echos General Milley's speech, supports the Constitution and opposes minority rule, insurrectionists, and demagogues/dictators.
SOME HIGHLIGHTS OF OUR WORK
Here are some highlights of our work.
We had considerable success at trial in the Marine Corps
immediately after law school. We spent all our time either in court or getting
ready to go to court. We did litigation work for Martin Marietta, winning two significant
cases in roughly two years. We won a big case for General Dynamics and one for Vogue
Instruments. We obtained injunctions in the U.S. District Court on bid protests
in Oklahoma for Eagle Picher and the Court of Federal Claims for Magnavox.
We had a lot of settlements along the way, including a $0.96
on-the-dollar settlement for a construction company named Goodfellow Brothers,
a fascinating story.
We won a significant precedent-setting data rights case in
the Court of Federal Claims, where the government misappropriated the contractor's
proprietary data. We won a major victory for AshBritt, which made it a
significant player in the disaster cleanup business. Congress had to change the
law due to the interpretation we argued.
We were retained on behalf of several clients to defend major asbestos claims in district courts nationwide, conceiving and initiating the government contractor defense. We were trial counsel in jury cases defending manufacturers of equipment containing asbestos. We also designed and prosecuted the case against the US government, forcing the government’s duty to indemnify the contractors for their losses.
(We grew our law firm from $2M in revenue to $80M.)
In the last decade, we handled 23 ASBCA and CBCA litigation matters, successfully resolving all but two, which we lost due to our client's admission against interest before our involvement.
As an example of the advantage of our experience, we pursued
precedent for a constructive change claim theory that no other attorney has prosecuted
based on our knowledge of case law we were taught in the 1960s, which is still a
good precedent. We also developed some trial tactics and techniques to speed up
claim resolution.
Last year, we settled two litigation matters for a large energy client on its energy savings contracts with the federal government. The more significant case involved contract language disputes that caused extended performance delays to the point that the client just wanted out of the contract. We devised and articulated the winning contract interpretation arguments and filed declaratory relief actions to get a judgment in the client's favor that could also avoid further performance on the contract. On the eve of the trial, the government agreed to make the client whole monetarily and relieved it of further obligation on the contract. A total victory was brought about by our articulation of contract language interpretation and the strategy of using declaratory relief as the vehicle for prompt judicial resolution.
Friday, October 13, 2023
IF YOU NEED TO GO TO TRIAL . . .
One subject we have avoided, as well we should, is trial work, strategy. and tactics. Does the commander announce his troop movements and share his plans with the enemy?
So, this will be brief.
As F. Lee Bailey did, we started in the Marine Corps in court every week. We learned direct and cross-examination, introduction of evidence, and how to argue to a jury or judge. Then in civilian life, we have been doing litigation work since Hector was a pup.
The point is whether the case goes to judgment or settles, we have had extraordinary success. We win.
But we also have some ideas on how to move the case faster, truncate discovery, avoid or hasten the trial date, sneak up on witnesses during an examination, and write short, pleasant-to-read, and compelling briefs.
Details are to be disclosed under the cloak of privilege.
https://spriggslawgroup.blogspot.com/2023/10/some-highlights-of-our-work.html
bill@spriggslawgroup.com