1. The
change proposal narrative containing:
(a) Summary statement of the change.
(b) Statement of the contract requirement.
(c) Statement of the Government direction or
actions or inactions that caused the contractor to exceed the contract
requirements.
(d) Detailed statements of the added work or
work performed exceeding contract requirements.
(e) Computation of the costs of work
exceeding contract requirements.
(f) (A Legal brief may be included in each
claim package or group of packages as the circumstances indicate.)
2. An
indexed and tabbed appendix containing, as applicable.
(a) Excerpts from pertinent contract
documents.
(b) Pertinent contract drawings.
(c) Pertinent correspondence and performance
documents.
(d) Charts and tables containing or analyzing
data.
(e) Photographs.
(f) Technical write-ups.
(g) Excerpts from technical treatises.
(h) Expert opinions.
(i) Cost computation.
(j) Any other pertinent documents or data.
(k) (Additional extremely detailed supporting
material of a bulky nature should be readily retrievable but not necessarily
appended to the change proposal.)
Each of the foregoing items of documentation for
the change proposal is described briefly below.
1(a). Summary. As the name implies, the summary statement is
a brief statement of the claim. It
should be complete including the amount claimed. However, it should never
consist of more than several short paragraphs.
Its purpose is to inform the reader of what he will learn if he reads
the rest of the change package. It is
important that the summary be accurate.
The summary should normally be prepared after all other writings, as set
out below, is completed.
1(b). Contract
Requirements. Since costs are being
claimed for exceeding contract requirements, it is essential that the original
contract requirements be clearly established at the beginning of the change
proposal. This is accomplished by
stating the contractor's interpretation of the contract requirement and then
proving it to be reasonable by reference to each and all of the specification
paragraphs, drawings or other contract documents upon which reliance is placed
for that particular interpretation. This
is the baseline that must be established. To avoid excess length in the
narrative, it frequently is desirable to include reproductions of contract
articles in the appendix, to which reference may be made. See Paragraphs
2(a), and (b) below.
1(c) The
Change. This is the paragraph that
will present some or the greatest difficulties in preparing, i.e., tying
performance exceeding contract requirements to the Government's action or
inaction (including issuance of defective or impossible drawings and
specifications). Where there is a
written document directing the contractor to do or not to do certain work (even
though not a formal change order), the problem is made easy. Where there was a document prepared rejecting
work considered to fulfill contract requirements, the problem is made
relatively easy. Likewise, where there
was a defect or incompatibility in the contract's drawings or specifications,
identification of the “constructive change” is relatively easy. However, it is not at all unusual for the
major portion of changes to arise from circumstances where the Government
gently nudged a contractor into a particular course of action. Some or all of the “nudges” may have been
oral, instead of written. The direction
in such areas is not direct but is more subtle.
For claim purposes it is necessary only that the government has participated
in the decision or the event that resulted in the contractor proceeding in a
certain manner.
It is particularly in this area of investigation
that the perception of the claim writers and investigators must be
exercised. For example, if difficulties
are encountered with the item to be manufactured, it may be because the
government changed the item's configuration (perhaps by work rejection) sometime
earlier. Similarly, for example, the claim investigators may not readily see
how a certain construction method or sequence was directed by the
Government. However, the reason for the
construction technique may have been the lack of trained personnel to do it in
another manner. The lack of trained
personnel in turn may have resulted from some direction that absorbed the
available skills in this area. In other
words, changes must be traced to their ultimate origin and at times one must
look behind the obvious and proximate causes for the real cause.
1(d). The
Added Work. The Government cannot
pay for work exceeding the contract requirements unless it knows precisely and
in detail what that excess work is.
Accordingly, it is necessary to describe by size, weight, length,
increased performance, etc., whatever it is that is being asserted as extra
work. Such description cannot be vague
or general, it must be specific.
Where the change is based upon a defect or incompatibility in the
drawings and specifications, a delay, a change of sequence, a redesign of work
or over-inspection, etc., the resulting extra work must be described with
particularity. It is not sufficient to
simply say that certain work was "delayed" or there was "impact."
The method by which the changes are quantified, i.e.,
the number of times an item was reworked, the number of drawing revisions, the
number of man hours and materials lost through a change or defect in drawings,
the increased quantities of materials used, etc., must be stated. This statement ties in with the cost
computation (1(e). below and it is not necessary to duplicate the quantities in
both sections. The purpose of the
present section is to make it clear that the change is for a certain quantity
of material, and/or labor, and/or delay, etc., and is not a change for
something else or something which cannot be quantified.
1(e). Cost
Computation. The computation of costs for the additional work is
principally the job of the accountants, change order estimators and cost
analysts. However, the claim writers and
investigators will contribute a major input in identifying quantities as
discussed in 1(d) above. In addition,
much of the pricing will be based upon engineering estimates which must be made
by the original investigating group.
1(f). Legal
Brief. A legal brief, if
appropriate, will be prepared by the attorneys who also will review and revise,
if necessary, the other sections of the change proposal narrative to coordinate
legal theory with provable fact.
Appendices
2(a). Contract. The use of contract excerpts is discussed in
Paragraph 1(b) above. Such excerpts
should be complete for this particular change proposal so that the parties
reviewing the claim need not go back to the contract itself.
2(b). Drawings. Same as 2(a) above.
2(c). Correspondence. These are documents generated during
performance and usually are included in the appendix to support the statements
in Paragraphs 1(c) and (d)., the work performed, and the Government's direction
to perform such work. Typically they may
include correspondence, minutes of meetings, test reports, but may consist of
any type of document. If they support
the claim and are not too bulky, include them in the appendix.
2(d). Chart
and Tables. Frequently raw data is
too voluminous to include in an appendix.
It should be charted, scheduled, tabulated, made into overlays, etc., in
such a manner as to support the claim.
It is extremely important that any such chart specifically reference the
source of the raw data and its retrievable location. Use of this type of material should be
maximized.
2(e). Photographs. "A picture is worth a thousand
words" is a saying that has particular applicability to proving
facts. Typically it not only proves the
fact of the change, but also is descriptive of what the change is. On the other hand photographs are dangerous
because they may show something inconsistent with a position asserted in some
other change proposal. They are
valuable, but use with caution.
2(g). Technical
Write-ups. Changes (and defective
specifications) frequently are based upon highly technical considerations. Frequently because of the length of the
necessary technical discussion, it is undesirable to include them in the change
proposal narrative and thus break the continuity and persuasiveness of the
narrative. Accordingly, it may be
desirable to summarize the technical discussion in the narrative and to present
it in complete detail in the appendix.
2(g). Technical
Treatises. Where technical
consideration are involved, it may be desirable to reproduce a few pages or a
chapter of an accepted technical treatise that supports the positions advanced.
2(h). Expert
Opinions. An expert opinion may be attached under the same consideration
discussed in 2(g) above.
2(i). Cost
Computation. Normally the narrative
(See 1(e). above) will contain only a summary of the cost
computation. Detail should be included
in the appendix. There will be another
layer of detail and raw data, work papers, etc., which will be available but
will not be included in the appendix and should be clearly referenced therein.
2(j). Other
Data. The above listing of
supporting documentation is not intended to be all inclusive and any other
material which may be considered persuasive should be included in the appendix.
The nature of appropriate material is
limited only by the nature of the material available and the imagination and
ingenuity of the people preparing the change proposal. Remember that after claim identification and
investigation, the major job becomes salesmanship. The first element of salesmanship is clear
statement of the change.
2(k). Bulky
Data. It is both impossible and
undesirable to include all supporting data in the appendix because of bulk and
also because much of it is of a lower tier evidentiary value. However, it should be identified, catalogued,
and available for presentation to the government should it request it or should
the circumstances later indicate the desirability of it being submitted. Much of the lower tier material would be
presented at a contract appeal hearing before the Armed Services Board of
Contract Appeals.
No comments:
Post a Comment